Resource-constrained Project Scheduling with Overlapping Activities Based on Extended Dependency Structure Matrix 预览 被引量:2

Resource-constrained Project Scheduling with Overlapping Activities Based on Extended Dependency Structure Matrix
在线阅读 免费下载
分享 导出
摘要 Dependency Structure Matrix( DSM) is a successful and powerful tool for representing and analyzing dependencies between the items,but for external influencing factors it cannot charge effectively. This paper sets the stage for connecting the activities and resources,which not only considers information flow but also resources constrains.We first introduce the DSM to represent the degree of overlapping between the activities in a project. Then we present the Extended DSM combined former DSM and resource factors to calculate the project duration. Finally,the practical significance of the Extended DSM is confirmed by an illustrative example. Dependency Structure Matrix (DSM) is a successful and powerful tool for representing and analyzing dependencies between the items, but for external influencing factors it cannot charge effectively. This paper sets the stage for connecting the activities and resources, which not only considers information flow but also resources constrains.We first introduce the DSM to represent the degree of overlapping between the activities in a project. Then we present the Extended DSM combined former DSM and resource factors to calculate the project duration. Finally, the practical significance of the Extended DSM is confirmed by an illustrative example.
作者 BAI Li-biao SONG Hong-yan BAI Si-jun GUO Yun-tao BAI Li-biao;SONG Hong-yan;BAI Si-jun;GUO Yun-tao;School of Management,Northwestern Polytechnical University;
机构地区 School of Management
出处 《国际设备工程与管理:英文版》 2013年第4期204-211,共8页 International Journal of Plant Engineering and Management
基金 The paper is supported by the National Natural Science Foundation of China under Grant No. 71172123, the Aviation Science Fund under Grant No. 2012ZG53083, the Soft Science Founda- tion of Shaanxi Province and the funds of NPU for Humanities and social sciences and management revilization under Grant No. RW201105
关键词 资源受限 结构矩阵 项目调度 帝斯曼 分析项目 影响因素 资源约束 计算项目 overlapped Extended DSM resource constraint project duration
作者简介 BAI Li-biao is now a Ph.D candidate in the School of Management, Northwest Polytechnical University. His research interests include Management Science and Engineering, Technical Economics & Management and Project Management. hanshannuanyang@ 163.com SONG Hong-yan is now a Master candidate in the School of Management, Northwest Polytechnical Uni- versity. Her research interests include Management Science and Management Engineering, Technical Economics and and Project Management BAI Si-jun is currently professor and doctoral tutor of School of Management, Northwestern Polytechnical University, His research interests include Management Science and Engineering, Systems Engineering and Project Management GUO Yun-tao is currently Associate School of Management, Northwestern Professor of Polytechnical University, His research interests include Manage Science and Engineering, Systems Engineering Project Management ment and
  • 相关文献

参考文献11

  • 1Roy G,Nava P,Isrel S. Integrating system analysis and project management tools[J].International Journal of Project Management,2002.461-468. 被引量:1
  • 2Yassine A,Falkenburg D,Chelst K. Engineering design management:an information structure approach[J].Int J Prod Res,1999,(13):2957-2975. 被引量:1
  • 3Browning T R. Applying the design structure matrix to system decomposition and integration problems:a review and new directions[J].{H}IEEE Transactions on Engineering Management,2001. 被引量:1
  • 4Chen C,Ling S F,Chen W. Project scheduling for collaborative product development using DSM[J].International Journal of Project Management,2003,(21):291-299. 被引量:1
  • 5Guo Y T,Xu J C,Bai S J. Project scheduling with overlapping activities using dependency structure matrix[A].2007.1167-1172. 被引量:1
  • 6Eppinger S D,Whitney D E,Smith R P,Gebala D A. A modelbasedmethod for organizing task in product development[J].Des,1994,(1):13. 被引量:1
  • 7Browning T R. Use of dependency structure matrices for product development cycle time reduction[A].{H}Tokyo,Japan,1998. 被引量:1
  • 8Maheswari J Uma,Varghese K. Project scheduling using dependency structure matrix[J].International Journal of project Management,2005,(23):223-230. 被引量:1
  • 9Steward D V. Systems analysis and management:structure,strategyand design[M].Princeton:Petrocelli Books,1981. 被引量:1
  • 10Chen Chun-Hsien,Ling S F,Chen W. Project scheduling for collaborative product development using DSM[J].International Journal of Project Management,2003,(21):291-299.doi:10.1016/S0263-7863(02)00023-6. 被引量:1

同被引文献37

  • 1彭武良,王成恩.关键链项目调度模型及遗传算法求解[J].系统工程学报,2010(1):123-131. 被引量:27
  • 2刘晓峰,陈通,张连营.基于微粒群算法的工程项目质量、费用和工期综合优化[J].土木工程学报,2006,39(10):122-126. 被引量:37
  • 3SMITH-PERERA A,GARCIA-MELON M,POVEDA-BAUTISTA R,et al.A project strategic index proposal for portfolio selection in electrical company based on the analytic network process[J].Renewable and Sustainable Energy Reviews,2010(37):1569-15789. 被引量:1
  • 4CARAZO A F,GOMEZ T,MOLINA J,et al.Solving a comprehensive model for multiobjective project portfolio selection[J].Computers&Operations Research,2010(14):630-639. 被引量:1
  • 5SABATIER V,MANGEMATIN V,ROUSSELLE T.From recipe to dinner:business model portfolios in the European biopharmaceutical industry[J].Long Range Planning,2010(43):431-447. 被引量:1
  • 6MESKENDAHL S.The influence of business strategy on project portfolio management and its success—a conceptual framework[J].International Journal of Project Management,2010,28(8):807-817. 被引量:1
  • 7RIJKE J,VAN HERK S,ZEVENBERGEN C,et al.Adaptive programme management through a balanced performance/strategy oriented focus[J].International Journal of Project Management,2014,32(7):1197-1209. 被引量:1
  • 8TIKKANEN H,KUJALA J,ARTTO K.The marketing strategy of a project-based firm:the four portfolios framework[J].Industrial Marketing Management,2007,36(2):194-205. 被引量:1
  • 9PARTINGTON D,PELLEGRINELLI S,YOUNG M.Attributes and levels of programme management competence:an interpretive study[J].International Journal of Project Management,2005,23(2):87-95. 被引量:1
  • 10JIANMU Y,SHENBAO Y,JING Z.On reallocation of failed project resource based on priority[J].Systems Engineering Procedia,2012,4:338-344. 被引量:1

引证文献2

二级引证文献1

投稿分析

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部 意见反馈